Mathematics
A software company sets up \(m\) number of computer systems to finish
an assignment in 17 days. If 4 computer systems crashed on the start
of the second day, 4 more computer systems crashed on the start of the
third day and so on, then it took 8 more days to finish the
assignment. The value of \(m\) is equal to
A
160
B
180
C
150
D
125